A provincial government study found that the collapse of a 68-tonne construction crane in Halifax during post-tropical Storm Dorian was the result of welding failure in the lower parts of the tower.

No one was killed or injured when the crane fell during the storm on September 7, 2019.

An engineering report included in the document released today concludes that the bend occurred in gusts of wind up to 107 kilometers per hour, even though the tower was designed for wind speeds of up to 160 km / h.

BMR Structural Engineering determined that the fault occurred in a section of the mast between six and nine meters above the base where a weld failed and a diagonal member of the mast was separated from a vertical member.

Continue reading:

The Halifax building was renamed after the collapsed crane in Hurricane Dorian

The story continues under the advertisement

According to the report, an analysis of the metal revealed corrosion, pores and cracks, as well as “other weld defects in welded joints”.

However, BMR determined that the crane was properly prepared for the storm and that it had been put into what is known as “weather vane mode”, in which the crane’s brakes are released and it is allowed to turn with the wind direction in a storm.

The report also states that the crane was inspected as necessary before it collapsed.

Trend stories

  • Canada’s travel ban on India and Pakistan will only delay the spread of COVID-19: Experts

  • Homeownership dreams for many young Canadians have been dashed as property prices rise

Overall, the investigation found that the owner and operator of a tower crane meets the safety standards of the province and Canada as well as all legal and regulatory requirements of the province.

“The investigation found that the weld failure caused the diagonal tube to detach from the vertical member of the mast and transfer the weight carried by the four vertical posts of the mast to only three of its posts, causing the tower section to rotate and fail,” it said it concluded in the report.


Click to play the video: 'Hurricane Dorian: crane lies on building, road after collapse during storm'


0:31
Hurricane Dorian: crane lies on top of the building, road after the collapse during the storm


Hurricane Dorian: crane lies on building by road after collapse during storm – September 7th 2019

The Department of Labor announced in a press release that it will meet with all tower crane owners and operators in the province to review the results of the investigation.

The story continues under the advertisement

The operators must ensure that all crane masts are “thoroughly cleaned, inspected and tested in order to identify defects or deterioration immediately”.

Continue reading:

It cost $ 2 million to remove the crane that crashed in Halifax during Dorian: Minister

The division says in the study, “It will task the industry with developing and implementing an industry-leading code of conduct or standard for the inspection, testing and maintenance of welds and booms on tower crane masts and booms in Nova Scotia.”

The provincial government announced in November 2019 that it would pay $ 2 million to clean up the collapsed crane and reopen the area. The former transport minister said the province was planning to make efforts to recover the money.

A class action lawsuit was filed in October 2019 to offset losses to businesses and tenants.